Safety paperwork on site: SWMS, inductions and toolbox talks

Updated 30 Sep 2026 · 5 min read

Good safety paperwork is short, written for the site, and actually used. Here's what the law expects on a construction site, what's good practice, and how to keep records you can find in a hurry.

Which safety laws apply

  • Every state and territory except Victoria uses the model Work Health and Safety (WHS) laws, with some local differences.
  • Victoria has its own Occupational Health and Safety (OHS) laws, run by WorkSafe Victoria. The ideas are similar, but the details differ. Check WorkSafe Victoria.
  • Your state's safety regulator is the place for local rules, forms and help.

SWMS for high risk construction work

A safe work method statement (SWMS) sets out the high risk construction work you'll do, the hazards, and how you'll control the risks. You need one before that work starts.

The WHS laws list 18 kinds of high risk construction work. They cover work:

  • where someone could fall more than 2 metres
  • on a telecommunication tower
  • demolishing load-bearing parts of a structure
  • that is likely to disturb asbestos
  • on structural alterations that need temporary support to stop a collapse
  • in or near a confined space
  • in or near a trench or shaft deeper than 1.5 metres, or a tunnel
  • using explosives
  • on or near pressurised gas mains or piping
  • on or near chemical, fuel or refrigerant lines
  • on or near live electrical installations or services
  • where the air may be contaminated or flammable
  • with tilt-up or precast concrete
  • on or next to a road, railway, shipping lane or other traffic corridor in use
  • where powered mobile plant is moving
  • in areas with artificial extremes of temperature
  • in or near water or other liquid where someone could drown
  • involving diving

Getting it right:

  • Who writes it. Whoever does the work is best placed, talking with the workers who'll do it. Usually that's the builder for their workers and the subbie for theirs.
  • Make it site-specific. A generic SWMS may not meet the law until it's been reviewed and changed for this site.
  • Keep it short. It must be easy to understand, including for workers whose first language isn't English. Pictures can help.
  • Follow it. If the work isn't being done the SWMS way, stop as soon as it's safe, then review it.
  • Principal contractors. On a construction project of $250,000 or more, the principal contractor must take reasonable steps to get a SWMS before high risk work starts.

In Victoria, WorkSafe Victoria's list of high risk construction work is very similar, and you also need a SWMS before the work starts. It notes that a job safety analysis (JSA) isn't the same as a SWMS. JSAs aren't required by law, but they're useful for other tasks.

General construction induction (White Card)

  • Everyone doing construction work needs general construction induction training, known as the White Card, before they start.
  • Workers must show their White Card to the business running the site, and to inspectors who ask.
  • White Cards are recognised Australia-wide.
  • If someone did the training more than 2 years ago and hasn't done construction work in the last 2 years, they must do it again before you let them on the tools.
  • In Victoria, the course must be face to face with an approved training provider. WorkSafe Victoria doesn't accept online White Card courses.

Site-specific inductions

The White Card covers construction in general. A site induction covers this site. Safe Work Australia's code of practice suggests it can include:

  • hazards on this site and how they're controlled
  • where underground services are
  • site safety rules and plans, such as the traffic management plan
  • who to report to and how to raise a safety issue
  • amenities, first aid and emergency procedures, including after-hours contacts
  • access, exits and site security

Visitors may need a short induction too. On housing jobs, subbies can induct their own workers for the builder, after talking it through with the builder. The builder should then check it's been done.

Toolbox talks

Toolbox talks and pre-start meetings are a quick way to share safety updates and hear from workers. Good topics include new high risk work starting, changes to site access, and anything that affects the public.

Good practice is to:

  • record the topic, who attended and any feedback
  • plan a regular program so workers get a say in how risks are controlled
  • check they're working, for example by tracking near misses

Keeping records

  • Keep the SWMS on site, or somewhere it can get to site quickly. An electronic copy is fine.
  • Keep it until the high risk work is finished. If there's a notifiable incident, keep it for at least 2 years after.
  • Keep induction sign-offs, White Card details and toolbox talk attendance with the job.

Sources

Checked September 2026. Rules change, and they differ between states. This is general information, not legal or tax advice.