An inspection and test plan (ITP) is the checklist for a stage of work: what to check, what “pass” means, and who signs. Fill it in on site and you have the record a certifier or auditor asks for.
Set up your ITPs once
Go to Settings → Templates → Inspection test plans and click New template.
Add one row per inspection point.
Say what to check and what “pass” means, like “50mm minimum cover to S-02”. Pick how it’s checked, who signs, and what evidence you want.
Make it a Hold point when the next stage has to wait until it passes, like reo before a pour. Make it a Witness point when someone should be told so they can attend.
Click Create template.
Jobs only show ITPs once you have a template, so builders who don’t use them never see them.
Fill it in on site
Open the job, click Field → ITP, pick a template and click Add ITP. On a phone, use Inspections on Today.
Click Inspect on a point, choose Pass, Fail or N/A, add a measurement, comment or photos, and click Save inspection.
No signal? On Today the inspection is saved on your phone and sent when you’re back online.
If a point fails, click Raise NCR. The NCR is filled in from the point, and the point links to it.
Once it’s fixed, click Re-inspect and record the new result.
The latest result counts. Earlier ones stay under Earlier inspections, so the record shows the fail, the NCR and the pass.
Get a certifier or engineer to sign
On the point, click Request sign-off, enter their name and email, and click Email sign-off link.
They get a personal link. It works once and expires after 14 days. They don’t need a Footing account.
On a hold point a certifier or engineer signs, only the office sends the link, so nobody on site can sign their own work off. If the site finds a problem first, click Record a fail.
They open it, record the result and sign.
The point shows when the link was emailed, opened and signed. The result records their name, role, email and signature.
Hold the next job until hold points pass
Turn on Hold the next job until hold points pass under Settings → Templates → Inspection test plans. A job then can’t be started while a job it waits on to finish has a hold point that hasn’t passed. Jobs linked to start or finish together don’t hold each other up.
Footing says which hold point is holding it up. Someone in the office can type a reason and click Start anyway; the reason goes on the job’s record. That covers the hold points open at the time: one that opens later holds the job again.
Only a job’s first start is checked. A job that has started can go on hold and carry on.
What happens next
An ITP is complete once every point has passed or is N/A. Quality → Inspections shows every ITP and any hold points still open; a project’s Quality tab shows its own. The job’s completion report lists each ITP and calls out hold points not released.
For your auditor or certifier
Open an ITP and click PDF record for every point, result, signer and NCR. Footing notes each download with a fingerprint of the file, so you can show a copy hasn’t been changed.